Cost Subsystem
Description

Cost estimate to convert a freeway shoulder lane into a MnPASS Lane on Corridor 4B. I-35W: TH 36 to Blaine.

Capital Cost Per Unit
$14,250,000.00
OM Cost Per Unit
$50,000.00
Adjusted Capital Cost Per Unit
$17,430,600.00
Adjusted O&M Cost Per Unit
$61,160.00
Reported Units
10.8 miles
Lifetime
20
Unit Cost Type
Unit
Per Mile
CPI ID
6
CPI Name

CIU1010000000710I

Year
2010
Notes
Total capital cost: $12 million to $16.5 million per mile (includes ATM and non-ITS infrastructure). ATM component: $16 million per corridor (includes tolling equipment, signs, sign structures, and communications infrastructure).